Medium-Term Plan of Priority Public Investment

This strategic document outlines the principles for implementing public investments over a medium-term period — 3 years — in line with national policy.

In particular, it identifies sectors and priority streams for public investment, the indicative allocation of funds from all sources, and cross-cutting strategic goals for implementing public investments.

The MTP serves as the foundation for effective planning, well-grounded project and program development, the formation of Single Project Pipelines, and optimal funding allocation.

The development of the MTP is governed by the Resolution of the Cabinet of Ministers of Ukraine No. 294 dated February 28, 2025. This resolution defines the procedure for developing and monitoring the implementation of the state's medium-term plan for priority public investments.

Period
01.01.2026 - 31.12.2028
Responsible Ministry
MINISTRY OF ECONOMY OF UKRAINE
51
Total streams
Investment streams by sector
2'164.1 bln
Total needs
Financial need by sector
581.3 bln
Total amount
Indicative total public investment ceiling
26.86%
Coverage rate
Financial need indicator
51
Total streams
Streams by strategic documents
Strategic Document
Funding Need
SectorLaw and Justice
Sub SectorDocumentary Heritage
Funding Need14'852'500 UAH
Development of a network of databases for storing insurance fund documentation in Ukraine
Implementor: MINISTRY OF JUSTICE OF UKRAINE
SectorLaw and Justice
Sub SectorPenal execution and probation
Funding Need3'572'731'900 UAH
Bringing the material, living, sanitary and hygienic conditions of detention of convicts and persons taken into custody into compliance with international standards
Implementor: MINISTRY OF JUSTICE OF UKRAINE
SectorEnergy Sector
Sub SectorElectric power industry
Funding Need6'201'194'350 UAH
Modernization and development of distribution electricity networks with the introduction of "smart grid" technologies
Implementor: MINISTRY OF ENERGY OF UKRAINE
SectorEnergy Sector
Sub SectorRenewable energy and alternative fuels
Funding Need12'438'687'000 UAH
Construction of wind power plants
Implementor: MINISTRY OF ENERGY OF UKRAINE
SectorEnergy Sector
Sub SectorElectric power industry
Funding Need32'535'740'450 UAH
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Implementor: MINISTRY OF ENERGY OF UKRAINE
SectorEnergy Sector
Sub SectorElectric power industry
Funding Need5'807'904'000 UAH
Modernization/renovation of installed generating capacities
Implementor: MINISTRY OF ENERGY OF UKRAINE
SectorEnergy Sector
Sub SectorElectric power industry
Funding Need29'922'485'000 UAH
Construction of new generating capacities
Implementor: MINISTRY OF ENERGY OF UKRAINE
SectorEnergy Sector
Sub SectorOil and gas industry
Funding Need2'599'364'000 UAH
Gas transportation
Implementor: MINISTRY OF ENERGY OF UKRAINE
SectorEnergy Sector
Sub SectorOil and gas industry
Funding Need15'606'373'000 UAH
Development and production of gas and oil
Implementor: MINISTRY OF ENERGY OF UKRAINE
SectorEnergy Sector
Sub SectorRenewable energy and alternative fuels
Funding Need0 UAH
Construction of small hydropower facilities
Implementor: MINISTRY OF ENERGY OF UKRAINE