State Single Project Pipeline

Within the Public Investment Management (PIM) reform being implemented by the Government of Ukraine, a unified approach to managing public investments is being introduced at the national, regional, and local levels. In particular, a legislative framework regulating PIM matters has been approved.

The procedure for forming the Single Project Pipeline (SPP) of public investments at the state, regional, and community levels is regulated by Cabinet of Ministers Resolution No. 527 of February 28, 2025. According to the procedure, the SPP contains a list of priority projects and programs from sectoral pipelines that have undergone expert appraisal and have been approved by the Strategic or Local Investment Council as eligible for the corresponding budget financing.

The formation of the SPP at state, regional and community levels through the DREAM ecosystem ensuring transparency and enabling review, analysis, and monitoring by sectoral ministries, international partners, IFIs, and the public. This enhances opportunities for attracting funding.

Information regarding projects and programs is displayed on the State Single Project Pipeline, in accordance with the decisions of the Strategic Investment Council, which are official and subject to mandatory use. At the same time, the public API of the system may temporarily display information that differs in certain particulars from the information published on the portal; such discrepancies are of a purely technical nature and shall be remedied in the prescribed manner.

Reform
CMU Resolution No. 527

All sectors
All streams
Project code
Keyword
Project coverage area
Number of alternative technical approaches

Current set filters (Filtered result: 1)

Project code: 110825-C8D5F273
Initiation date
Budget
Status
State level of SPP
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

The project to improve the efficiency of electricity transmission (modernization of substations)

Project goal
Improving the condition of infrastructure. Increasing compliance with modern standards
Geography
All Ukraine
Initiator
PRIVATE JOINT STOCK COMPANY "NATIONAL ENERGY COMPANY "UKRENERGO"
The project to improve the efficiency of electricity transmission (modernization of substations)
not provided
In December 2015, a contract was signed with the consortium "GE Grid GmbH" (Germany) and LLC "Chornomorenergospetsmontazh" (Ukraine) for the supply of equipment and technical re-equipment of the 330 kV substation "Kryvorizhska" and the 330 kV substation "Dnipro-Donbas". In August 2022, the reconstruction of the 330 kV substation "Kryvorizhska" was completed and the facility was put into operation. Work on the 330 kV substation "Dnipro-Donbas" was suspended by the Contractor due to the introduction of martial law. The procedure is underway. termination of the contract due to force majeure circumstances associated with the armed aggression of the Russian Federation against Ukraine. In March 2024, final settlements were made with LLC «CHESM» (for equipment, services provided) for the technical re-equipment of the 330 kV substation «Kryvorizka».The project provides for:- Increasing reliability, reducing the accident rate in the operation of substations by installing modern electrical equipment manufactured using new materials and modern technologies;- Reducing costs during preventive maintenance (maintenance) by installing a reliable element base of RPA devices and power electrical equipment components;- Reducing emergency repair costs by updating equipment and reducing the use of consumables thanks to manufacturer warranties;- Increasing the reliability of generating capacities due to more reliable operation of power transmission networks, as well as increasing the reliability of electricity transit at the regional level and at the level of the Unified Power System of Ukraine as a whole.
Budget1'951'852'953 UAH
Implementation period204 months