Alternative solution 1 using wind turbines with lower unit capacity
Alternative solution 2 using wind turbines with higher unit capacity
The solution involves the construction of a wind farm with a total capacity of 297 MW using wind turbines with a lower unit capacity (4.5 MW); total number of wind turbines: 66 units. Compared to wind turbines with a higher capacity, the specific cost of wind turbines and the cost of service per 1 MW, the utilization factor of installed capacity (approximately 43.0%) is higher.
Project cost25'351'016'158 UAH
Implementation period53 months