52,75 mln
Cost
Estimated project costs by sectors
Project code
Keyword
Budget
Status
Stream

Current set filters (Filtered result: 1)

Project code: 170226-E11142A4
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date02. 2026
SectorCulture and information
SubsectorCultural Heritage and National Memory
StatusInvestment Feasibility Study

Restoration (repair and restoration) of the building and the adjacent territory as a single complex architectural ensemble of the municipal library at 22 Ukrainian Street in Chernivtsi

Project goal
Improving the quality of services. Improving the condition of infrastructure
Geography
Chernivetska community, Chernivtsi city
Initiator
DEPARTMENT OF INFRASTRUCTURE AND WELFARE OF CHERNIVET CITY COUNCIL
Restoration (repair and restoration) of the building and the adjacent territory as a single complex architectural ensemble of the municipal library at 22 Ukrainian Street in Chernivtsi
Current repairs and partial modernization of the municipal library building at 22 Ukrainian Street
The project provides for strengthening and restoring foundations and load-bearing walls, repairing and strengthening brick vaults of basements, eliminating the causes of dampness and installing waterproofing. It is planned to repair and partially replace roof structures, restore wooden roof elements, repair the drainage system, restore facades and architectural details. The engineering solutions include the reconstruction of water supply and drainage systems, updating the heating system, installing ventilation with recuperation, replacing electrical networks and lighting with energy-saving ones, as well as installing fire alarm and lightning protection systems. The project also provides for ensuring barrier-free access to the building (installing a lifting platform, adapting entrances) and landscaping the adjacent territory with arranging the coating and drainage.
Budget52'750'567 UAH
Implementation period60 months