204,32 mln
Cost
Estimated project costs by sectors
Project code
Keyword
Project cost
Status
Stream
Initiation date
Project cost
Status
Local level of SPP
Local level of SP
Date04. 2026
SectorEducation and science
SubsectorSchool education
StatusInvestment Feasibility Study

Modernization of the educational space and updating of the material and technical base of the Educational Complex "Comprehensive School of I-III Degrees No. 3 - Collegium" of the Smilyansk City Council, Cherkasy Region

Project Goal
Increasing compliance with modern standards. Increasing compliance with modern standards, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Improving the quality of services
Geography
Smila city
Initiator
EDUCATIONAL COMPLEX "COMPLETE SCHOOL OF GRADES I - III №3 - COLLEGE" OF SMILIAN CITY COUNCIL OF CHERKASY REGION
Complete modernization of the educational space and updating of the material and technical base of the Educational Complex "Comprehensive School of I-III Degrees No. 3 - Collegium" of the Smilyansk City Council, Cherkasy Region
Complete equipment of 3 classrooms of the mathematics cycle of the educational space and updating of the material and technical base of the Educational Complex "Comprehensive School of I-III Degrees No. 3 - Collegium" of the Smilyansk City Council, Cherkasy Region
Equipping 6 classrooms with the latest equipment, furniture, computer and multimedia technology in order to create a modern educational environment and to implement the requirements of the National University of Science and Technology and specialized education.
Project cost9'672'984 UAH
Implementation period7 months
State level of SP
Local level of SPP
Local level of SP
Date04. 2026
SectorEducation and science
SubsectorSchool education
StatusInvestment Feasibility Study

Modern educational space in the Educational Complex "Lyceum - Comprehensive School of I-III Degrees "Leader" of the Smilyansk City Council, Cherkasy Region

Project Goal
Increasing compliance with modern standards. Improving the condition of infrastructure, Improving the quality of services
Geography
Smila city
Initiator
DEPARTMENT OF EDUCATION, YOUTH AND SPORTS OF THE SMILAN CITY COUNCIL
Comprehensive arrangement of six classrooms for the natural sciences and mathematics cycle
Partial renovation of the material and technical base of the science and mathematics classrooms
The project involves comprehensively equipping six classrooms of the natural science and mathematics cycle with modern laboratory, computer and interactive equipment. As part of the implementation, it is planned to purchase demonstration devices, digital measuring complexes, STEM sets, multimedia equipment and ergonomic furniture, which will provide the opportunity to implement practice-oriented learning, conduct research and use digital educational tools in the daily educational process.
Project cost6'998'964 UAH
Implementation period7 months
Local level of SPP
Local level of SP
Date03. 2026
SectorMunicipal infrastructure and services
SubsectorDevelopment and Reconstruction of Subnational Infrastructure
StatusInvestment Feasibility Study

Arrangement of a barrier-free route connecting "Administrative Services Center - Smilyansk City Hospital on Sofiivska Street"

Project Goal
Ensuring inclusiveness and equal opportunities. Increasing compliance with modern standards, Improving the condition of infrastructure
Geography
Smila city
Initiator
DEPARTMENT OF HOUSING AND MUNICIPAL MANAGEMENT OF THE EXECUTIVE COMMITTEE OF SMILYANSK CITY COUNCIL
Maturity level
88
Major repairs of sidewalks on the barrier-free route
Current sidewalk repairs on the barrier-free route
Overhaul involves a comprehensive renovation of the sidewalk infrastructure on a specific route with a complete replacement of the pavement, lowering the curbstone, installing tactile tiles, adapting pedestrian crossings, and removing physical obstacles for people with limited mobility in order to create a barrier-free pedestrian environment.
Project cost35'340'000 UAH
Implementation period8 months
Local level of SPP
Local level of SP
Date03. 2026
SectorMunicipal infrastructure and services
SubsectorDistrict Heating
StatusInvestment Feasibility Study

Reconstruction of boiler room No. 7 of the KP "Smilakomunteploenergo" in the city of Smila, Cherkasy region, by installing (connecting) a cogeneration unit.

Project Goal
Improving the quality of services. Improving the equality of wealth distribution, Introducing innovations and energy-efficient solutions
Geography
Smila city
Initiator
UTILITY ENTERPRISE "SMILAKOMUNTEPLOENERGO"
Maturity level
83
Reconstruction of boiler room No. 7 of the KP "Smilakomunteploenergo" in the city of Smila, Cherkasy region, by installing a cogeneration unit with a capacity of 530 kW
Reconstruction of boiler room No. 7 of the KP "Smilakomunteploenergo" in the city of Smila, Cherkasy region, by installing a solar power plant
The project plans to reconstruct the existing gas boiler house by installing (connecting) a 530 kW cogeneration unit on its territory to generate electricity and heat. The existing boiler house is completely dependent on external electrical networks, which, in the conditions of a systemic power shortage in the Ukrainian energy system, reduces its ability to produce and transport heat to end consumers. The existing boiler house is equipped with a backup power source (diesel generator), but such a solution is short-term, since it only helps to temporarily support the system. Using a backup power source for long-term/continuous operation of the boiler house in today's conditions is not relevant, as it requires constant fuel consumption and creates an excessive financial burden on the enterprise. By installing a cogeneration unit, the existing boiler house will be able to switch to a high-tech combined cycle of operation, and the useful use of a unit of natural gas will double, because the boiler house will produce not only heat energy, but also electricity. Due to the fact that the boiler house with a CHP will produce electricity at the place of consumption (self-sufficiency), losses during its transportation will be reduced. Thus, the operating boiler house will gain the ability to operate autonomously in blackouts, which guarantees uninterrupted provision of services to the population.
Project cost10'572'853 UAH
Implementation period10 months
Local level of SPP
Local level of SP
Date03. 2026
SectorMunicipal infrastructure and services
SubsectorDistrict Heating
StatusInvestment Feasibility Study

Reconstruction of boiler room No. 1 of the KP "Smilakomunteploenergo" in the city of Smila, Cherkasy region, by installing (connecting) a cogeneration unit.

Project Goal
Improving the quality of services. Capacity building, Improving the equality of wealth distribution, Introducing innovations and energy-efficient solutions
Geography
Smila city
Initiator
UTILITY ENTERPRISE "SMILAKOMUNTEPLOENERGO"
Maturity level
79
Reconstruction of boiler room No. 1 of the KP "Smilakomunteploenergo" in the city of Smila, Cherkasy region, by installing (connecting) a cogeneration unit with a capacity of 530 kW.
Reconstruction of boiler room No. 1 of the KP "Smilakomunteploenergo" in the city of Smila, Cherkasy region, by installing a solar power plant
The project plans to reconstruct the existing gas boiler house by installing (connecting) a 530 kW cogeneration unit on its territory to generate electricity and heat. The existing boiler house is completely dependent on external electrical networks, which, in the conditions of a systemic power shortage in the Ukrainian energy system, reduces its ability to produce and transport heat to end consumers. The existing boiler house is equipped with a backup power source (diesel generator), but such a solution is short-term, since it only helps to temporarily support the system. Using a backup power source for long-term/continuous operation of the boiler house in today's conditions is not relevant, as it requires constant fuel consumption and creates an excessive financial burden on the enterprise. By installing a cogeneration unit, the existing boiler house will be able to switch to a high-tech combined cycle of operation, and the useful use of a unit of natural gas will double, because the boiler house will produce not only heat energy, but also electricity. Due to the fact that the boiler house with a CHP will produce electricity at the place of consumption (self-sufficiency), losses during its transportation will be reduced. Thus, the operating boiler house will gain the ability to operate autonomously in blackouts, which guarantees uninterrupted provision of services to the population.
Project cost10'572'853 UAH
Implementation period10 months
Local level of SPP
Local level of SP
Date02. 2026
SectorEducation and science
SubsectorSchool education
StatusInvestment Feasibility Study

Creation of an educational space within the framework of the "New Ukrainian School" reform - Smila Urban Territorial Community

Project Goal
Increasing compliance with modern standards. Increasing compliance with modern standards, Improving the quality of services
Geography
Smila city
Initiator
DEPARTMENT OF EDUCATION, YOUTH AND SPORTS OF THE SMILAN CITY COUNCIL
Maturity level
88
Phased renovation of educational spaces of seven educational institutions
Local phased renewal of educational space within one educational institution
Phase-by-step procurement of a basic set of furniture and (or) necessary educational equipment for eight classrooms in 7 educational institutions. The renovation is carried out within the framework of functional modernization of the premises without interference with the structural elements of the building or engineering systems.
Project cost1'222'900 UAH
Implementation period6 months
Local level of SPP
Local level of SP
Date12. 2025
SectorMunicipal infrastructure and services
SubsectorUrban planning and landscaping
StatusInvestment Feasibility Study

Major renovation of part of the sixth floor of the building of the outpatient department of the KNP "Smilyansk City Hospital" by SMR at 82 Heroiv Kholodnoyartsiv St., Smila, Cherkasy region

Project Goal
Creation of new facilities and services. Improving the quality of services
Geography
Smila city
Initiator
MUNICIPAL NON-COMMERCIAL ENTERPRISE "SMILYANSKA CITY HOSPITAL" OF SMILYANSKA CITY COUNCIL
Maturity level
67
Major renovation of the sixth floor premises with replacement of existing networks
Major renovation of the hemodialysis unit
The decision concerns major overhaul. Installation of systems: Water supply and water purification (to provide dialysis machines). Sewage, isolation of wastewater from the dialysis area. Heating, ventilation and air conditioning with maintenance of air sterility. Power supply and lighting, including emergency. Installation of a medical gas system (oxygen, vacuum). Arrangement of sanitary facilities, staff rooms, sterile area, room for osmosis machines. Interior decoration in accordance with the requirements for medical institutions (ease of cleaning, antiseptic surfaces).
Project cost8'798'619 UAH
Implementation period15 months
Local level of SPP
Local level of SP
Date12. 2025
SectorMunicipal infrastructure and services
SubsectorUrban planning and landscaping
StatusInvestment Feasibility Study

Major renovation of the third floor of the building of the general practice family medicine outpatient clinic No. 1 of the KNP "CPMSD" SMR

Project Goal
Improving the condition of infrastructure. Increasing compliance with modern standards
Geography
Smila city
Initiator
MUNICIPAL NON-COMMERCIAL ENTERPRISE "CENTER OF PRIMARY MEDICAL AND SANITARY AID" OF SMILYANSK CITY COUNCIL
Maturity level
43
Major renovation of the third floor of the building
Current renovation of the third floor of the building
Overhaul of premises and networks on the third floor of the building of the general practice family medicine outpatient clinic No. 1 of the KNP "CPMSD" SMR
Project cost6'000'000 UAH
Implementation period14 months
Local level of SPP
Local level of SP
Date12. 2025
SectorHealthcare
SubsectorSpecialized medical care
StatusInvestment Feasibility Study

Major repair of the elevator shaft with the installation of a freight elevator of the main medical building of the KNP "Smilyansk City Hospital" SMR at the address of the city of Smila, 82 Heroiv Kholodnoyartsiv St., Cherkasy region

Project Goal
Improving the condition of infrastructure. Ensuring inclusiveness and equal opportunities, Improving the quality of services
Geography
Smila city
Initiator
MUNICIPAL NON-COMMERCIAL ENTERPRISE "SMILYANSKA CITY HOSPITAL" OF SMILYANSKA CITY COUNCIL
Maturity level
47
Installation of a new elevator with repair of the elevator shaft
Installation of a new elevator without repairing the elevator shaft
The project involves major repairs to the existing elevator shaft of the main medical building in order to bring its design into line with modern safety, reliability and operation requirements. After the completion of the repairs, it is planned to install a new modern freight elevator for medical purposes.
Project cost2'285'000 UAH
Implementation period28 months
State level of SP
Local level of SPP
Local level of SP
Date11. 2025
SectorEducation and science
SubsectorSchool education
StatusInvestment Feasibility Study

Major repairs of the catering unit of the Smila comprehensive school of grades I-III No. 11 of the Smila city council of Cherkasy region at the address: 47 Repina St. in the city of Smila, Cherkasy region

Project Goal
Increasing compliance with modern standards. Introducing innovations and energy-efficient solutions, Improving the quality of services
Geography
Smila city
Initiator
SMILIAN COMPREHENSIVE SCHOOL FOR GRADES I - III №11 OF SMILIAN CITY COUNCIL OF CHERKASY REGION
Maturity level
79
Major repairs of the catering unit of the Smila comprehensive school of grades I-III No. 11 of the Smila city council of Cherkasy region at the address: 47 Repina St., in the city of Smila, Cherkasy region
Construction of a new modular energy-efficient catering unit on the territory of Smila Secondary School No. 11 of Smila City Council, Cherkasy Region at the address: 47 Repina St., Smila, Cherkasy Region
The project includes measures to carry out major repairs to the catering unit, replace utility networks, update the dining hall and food preparation and distribution areas, the washing area, the food storage area, and equip them with modern energy-efficient technological equipment and furniture. The project provides for improving the working conditions of the catering unit staff and ensuring accessibility for students with limited mobility.
Project cost17'794'696 UAH
Implementation period14 months

In focus

All news