New construction of domestic sewage treatment plants on Zavodska Ploshcha St., Horodok
Construction of sewage pumping stations, reconstruction of the sewage network and reconstruction with completion of existing treatment facilities in the city of Horodok
Construction of treatment facilities with a capacity of 1500 m3/day using continuous flow technology with a complete biological treatment of household wastewater BIOPAX. Three stages of wastewater treatment are used:
- first stage: mechanical treatment performed by a sand screen, after which the BOD5 indicator decreases by 10%;
- second stage: biological treatment in a circulating reactor with a secondary settling tank;
- third stage: biological additional treatment of wastewater in a hydroponic flowing lagoon, which returns wastewater to a natural state. The entire complex of technological facilities is located in one hall.
Project cost149'450'000 UAH
Implementation period23 months