Khersonska

community since 2020


About the community
Community SPP
Community SP
Community MTP
Project archive
All sectors
All streams
1
Projects
Projects by sectors
1
Projects
Projects by goal
1
Projects
Projects by status
229,23 mln
Cost
Estimated project costs by sectors
Project code
Keyword
Budget
Status

Current set filters (Filtered result: 1)

Project code: 080126-717CC373
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date01. 2026
SectorMunicipal infrastructure and services
SubsectorDistrict Heating
StatusPreliminary Investment Feasibility Study

Reconstruction of heating networks of the boiler house at 95 I. Bohuna St. in the city of Kherson. Sections from the boiler house to TK-130; from TK-120 to TK-8-1; from TK-211 to TsTP-22; from TK-211 to TK-214; from TK-212/1 to TsTP-21

Project Goal
Improving the condition of infrastructure. Improving the quality of services
Geography
Khersonska community
Initiator
Department of Municipal Economy of the Kherson City Council
Maturity level
87
Reconstruction of heating networks of the boiler house at 95 I. Bohuna St. in the city of Kherson. Sections from the boiler house to TK-130; from TK-120 to TK-8-1; from TK-211 to TsTP-22; from TK-211 to TK-214; from TK-212/1 to TsTP-21
Reconstruction of the boiler room at 95 I. Bohuna Street with the installation of modular boiler rooms
For 2026 - 2028, it is planned to carry out work on partial replacement of pipelines using heat-insulated pipes and pipe elements with a steel conductive pipe for heat supply with a heat-insulating layer of foamed polyurethane and a covering layer with a polyethylene shell. Renovation of the heat supply system improves energy efficiency, reduces operating costs and ensures reliable operation.
Project cost0 UAH
Implementation period33 months