Kharkivska

community since 2020


About the community
Community SPP
Community SP
Community MTP
Project archive
All sectors
All streams
1
Projects
Projects by sectors
1
Projects
Projects by goal
1
Projects
Projects by status
312,2 mln
Cost
Estimated project costs by sectors
Project code
Keyword
Budget
Status

Current set filters (Filtered result: 1)

Project code: 101025-11AFC3F2
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date10. 2025
SectorMunicipal infrastructure and services
SubsectorWater supply and sanitation
StatusInvestment Feasibility Study

Reconstruction of the off-site water supply system of the city of Lozova, Kharkiv region, water mains D=600-1000mm, L1=33.128 km and L2=32.785 km. inventory No. 44055, 44056, 44057 and with an internal site pipeline

Project Goal
Improving the quality of services. Improving the condition of infrastructure
Geography
Krasnopavlivka town
Initiator
UTILITY ENTERPRISE "KHARKIVVODOKANAL"
Maturity level
84
Reconstruction of the off-site water supply system of the city of Lozova, Kharkiv region, water mains D=600-1000mm, L1=33.128 km and L2=32.785 km. inventory No. 44055, 44056, 44057 and with an on-site pipeline
Not provided
The project provides for: Reconstruction of pipelines with a total length of 65,913 thousand m is carried out by the method of rehabilitation using pipes that are guaranteed to transport the volume of water specified in the initial data, taking into account their quantitative and qualitative state, as well as to take on the existing vertical load from the soil throughout the subsequent service life of the water supply system. The recommended pipe diameter is D=500mm, pipe material is polyethylene PE 100 SDR 11- from NS to PK 153, from PK153 to the RCV of the city of Lozova - PE 100 SDR 17. The total maximum water flow rate for which the hydraulic work of the main water supply systems should be calculated should be 15955 m³/day. At the same time, the minimum calculated flow rate is 4500 m³/day.
Project cost299'600'000 UAH
Implementation period18 months

In focus