Konotopska

community since 2020


About the community
Community SPP
Community SP
Community MTP
Project archive
All sectors
All streams
1
Projects
Projects by sectors
1
Projects
Projects by goal
1
Projects
Projects by status
71,1 mln
Cost
Estimated project costs by sectors
Project code
Keyword
Budget
Status

Current set filters (Filtered result: 1)

Project code: 021225-AE6375FB
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date12. 2025
SectorMunicipal infrastructure and services
SubsectorUrban planning and landscaping
StatusPreliminary Investment Feasibility Study

Construction of a cogeneration plant for energy supply of facilities of the Konotop Transport Department

Project Goal
Introducing innovations and energy-efficient solutions. Improving the condition of infrastructure
Geography
Konotopska community, Konotop city
Initiator
DEPARTMENT OF HOUSING AND MUNICIPAL MANAGEMENT OF THE KONOTOP CITY COUNCIL OF THE SUMY REGION
Maturity level
77
Construction of a cogeneration plant for energy supply of facilities of the Konotop Transport Department
Installation of a solar station for electricity supply of the Konotop Transport Department
The project provides for the energy supply of the facilities of the KP "KTU", consisting of a wood waste storage facility, a chip crusher, a storage bunker for finished chips, preparation and transfer of raw materials to the gasifier unit, equipment to ensure the functioning of the gasifier, final purification of the obtained generator gas, a container cogeneration module with communications for its functioning, as well as the transmission of electricity and heat to consumers, including the distribution of electricity between the DEPO, tram traction substations and complete transformer substations for street lighting in the city.
Project cost70'100'000 UAH
Implementation period30 months