Sambirska

community since 2020


About the community
Community SPP
Community SP
Community MTP
Project archive
Project code
Keyword
Initiator
Project/program objective
Budget
Status
Sector
Stream

Current set filters (Filtered result: 0)

Project code: 241125-34ACC536
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date11. 2025
SectorMunicipal infrastructure and services
SubsectorWater supply and sanitation
StatusInvestment Feasibility Study

Application of solar energy for the needs of increasing the reliability of the water supply and wastewater systems of the city of Sambir (construction of a solar power plant at stations I and II of the Sambir VUVKG lift)

Project goal
Introducing innovations and energy-efficient solutions. Contribution to climate or environmental goals, Increasing compliance with modern standards, Creation of new facilities and services, Improving the condition of infrastructure, Improving the quality of services
Geography
Sambir city
Initiator
DEPARTMENT OF CAPITAL CONSTRUCTION AND HOUSING AND UTILITIES OF THE EXECUTIVE COMMITTEE OF SAMBIR CITY COUNCIL
Application of solar energy to increase the reliability of the water supply and wastewater systems of the city of Sambir (construction of a solar power plant at stations I and II of the Sambir VUVKG lift)
Installing a solar power plant at only one lift station or with a lower capacity.
Replacing equipment and pumps with energy-efficient ones without installing a solar power plant
The project involves the construction of an industrial solar power plant at stations I and II of the Sambirsk VUVKG lift to ensure partial or full coverage of the electricity consumption of pumping stations and technological sites of the enterprise. The main goal is to increase energy independence and stability of the critical water supply and wastewater infrastructure, reduce the risks of water supply interruptions and optimize electricity costs. The solar power plant will ensure stable energy supply to pumping units during peak loads and emergencies, reduce electricity costs and reduce CO₂ emissions, which is in line with the goals of sustainable development and the climate obligations of the community. The project involves integrating the solar power plant with the existing dispatching and energy management system of the enterprise, which allows for automatic regulation of the operation of pumps depending on the solar energy generated. Installing solar power plants at two lifting stations ensures scalability and redundancy of the generated energy, which increases the reliability of water supply and wastewater disposal for the entire city. Thanks to an integrated approach, including connection to the grid and a monitoring system, the enterprise receives long-term cost savings, reduced environmental impact, and strengthened energy security of the community.
Budget9'320'000 UAH