Project code: 041125-86FE7F55
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date11. 2025
SectorEnvironment
SubsectorWaste management, including radioactive waste
StatusInvestment Feasibility Study

Reconstruction of the MSW landfill in Sambor, Lviv region. Correction

Project goal
Contribution to climate or environmental goals. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure
Geography
Sambir city
Initiator
DEPARTMENT OF CAPITAL CONSTRUCTION AND HOUSING AND UTILITIES OF THE EXECUTIVE COMMITTEE OF SAMBIR CITY COUNCIL
Reconstruction of the MSW landfill in Sambor, Lviv region
Complete liquidation of the landfill with transportation of waste to other landfills
Partial reclamation without modernization of engineering systems
The comprehensiveness of environmental problem solving is guaranteed by the implementation of a set of technological, organizational and other measures. To ensure the regulatory state of the environment and environmental safety, the project envisages developing 2 solid waste storage maps with the installation of protective dams, building a waste sorting complex, a leachate disinfection station, water supply ditches, control ponds, a drainage system for leachate removal, a weighing station, structures for protection against spontaneous combustion of waste and atmospheric pollution, a power plant, and access roads.
Budget92'582'729 UAH
Implementation period24 months

In focus