Ratnivska

community since 2020


About the community
Community SPP
Community SP
Community MTP
Project archive
All sectors
All streams
1
Projects
Projects by sectors
1
Projects
Projects by goal
1
Projects
Projects by status
24,95 mln
Cost
Estimated project costs by sectors
Project code
Keyword
Budget
Status

Current set filters (Filtered result: 1)

Project code: 120226-0401D60F
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date02. 2026
SectorEducation and science
SubsectorSchool education
StatusInvestment Feasibility Study

Major repairs (thermal modernization) of the premises of building No. 1 of the Brody Lyceum of the Ratnivka Village Council at 4 Ozernaya Street in the village of Brody, Kovelsky district, Volyn region

Project Goal
Increasing compliance with modern standards. Increasing compliance with modern standards, Introducing innovations and energy-efficient solutions
Geography
Brody village
Initiator
Brody Lyceum of Ratnivka Village Council
Maturity level
82
Major repairs (thermal modernization) of the premises of building No. 1 of the Brody Lyceum of the Ratnivka Village Council at 4 Ozernaya Street in the village of Brody, Kovelsky district, Volyn region
Construction of a new building in Building No. 1 of the Brody Lyceum of the Ratnivka Village Council
Thermomodernization of the Brody Lyceum of the Ratnivka Village Council is an important step towards improving learning conditions and increasing the energy efficiency of the building. The project is aimed at improving the technical condition of the enclosing structures and creating comfortable conditions for participants in the educational process. The implementation of the Project and relevant measures will ensure maximum energy savings and reduce energy costs. Thanks to insulation, classrooms become more comfortable, humidity and the risk of mold are reduced. In addition, the appearance of the building's facades will improve and its service life will be significantly extended. At the same time, the project has great social significance, since its implementation is aimed at improving the quality and conditions for providing educational services, and will also allow optimizing budget expenditures. This is an important contribution to creating a safe, healthy and modern educational space.
Project cost24'950'000 UAH
Implementation period24 months