New construction of a roundabout at the intersection of Prosvity-Khimikiv Streets in Ivano-Frankivsk
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the construction of a new roundabout at the intersection of Prosvita Street and Khimikiv Street in Ivano-Frankivsk. The solution is aimed at replacing the existing transport hub, which does not fully provide the proper level of safety and capacity in the conditions of increasing traffic intensity and the formation of a new exit to the bridge from Khimikiv Street. The project involves the construction of a roundabout, approaches to it, sidewalks, pedestrian and bicycle infrastructure, pedestrian crossings, outdoor lighting, drainage, traffic management, landscaping and barrier-free measures. The implementation of the project will ensure a reduction in the number of conflict points, increased safety for all traffic participants, improved transport accessibility, more stable passage of traffic flows and better integration of existing and new street and road infrastructure in the northern part of Ivano-Frankivsk
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Improving the equality of wealth distribution
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other functional
2471.3 m2
Strategic Case
Strategic feasibility of the project
Sector
Transport Sector
Subsector
Road transport and road infrastructure
Stream
Development and restoration of public road infrastructure
Strategic document
Стратегія розвитку територіальної громади
Task
B.5 Development of the city's transport infrastructure
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
New construction of a roundabout at the intersection of Prosvity-Khimikiv Streets in Ivano-Frankivsk
Technical Solution 2
Reconfiguration of an existing intersection with the installation of traffic light regulation and additional accumulation lanes
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]