Modernization of the educational space of the scientific lyceum


Sector
Education and science
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SP
Implementation
Completion

General information

Description of the project

Creating a modern, safe and innovative educational environment in the scientific lyceum by updating the material and technical base, introducing digital technologies and modernizing educational spaces in accordance with the requirements of the New Ukrainian School.

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Increasing compliance with modern standards, Improving the equality of wealth distribution, Ensuring inclusiveness and equal opportunities, Improving the quality of services

Description of the purpose of the project and ways to achieve it

The project involves a comprehensive modernization of the educational space of the lyceum, including: - renovation of classrooms (biology, chemistry, physics, STEM) - purchase of modern laboratory equipment - arrangement of interactive learning areas - purchase of multimedia equipment (interactive panels, projectors) - renovation of furniture (ergonomic, mobile) - creation of a safe educational environment (lighting, ventilation, fire safety) - renovation of classrooms The project is focused on developing students' research skills, critical thinking and preparation for modern challenges.

Problems and solutions resulting from project implementation

The project implementation involves: • complete renovation of the material and technical base • introduction of interactive learning technologies • creation of a flexible educational space • increasing the level of security • adaptation of premises to modern standards

Socio-economic context

Indicator

Value

Number of IDP users

30 human

Number of employees of the institution/institution/organization

49 human

Number of people who will use the service

520 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform

Strategic document

Стратегія розвитку територіальної громади

Task

D.1. Innovative education, quality education

Project objectives

Indicator
Base value
Target value
Number of classrooms in the Ivano-Frankivsk Scientific Natural and Mathematical Lyceum named after Ivan Pulyuy, which are equipped with modern equipment for the implementation of the State Standard of Basic Secondary Education
0 units
4 units

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Аналіз інформації щодо прогнозованої кількості учнів, які після отримання базової освіти продовжать здобувати повну загальну середню освіту у ІФНПМЛ
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
530 human
Annual demand for services/infrastructure
2
555 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic analysis.docx
14.04.2026
16:02:44 UTC

Alternative technical solutions

Technical Solution 1

Comprehensive modernization of the educational space of the scientific lyceum by creating modern classrooms with a complete renovation of the material and technical base.

Technical Solution 2

Partial renovation of the educational space by replacing individual elements of the material and technical base.

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)7'500'000 UAH3'000'000 UAH
For preparation1'500'000 UAH0 UAH
For implementation6'000'000 UAH3'000'000 UAH
Project operation and closure cost0 UAH2'000 UAH
For operation0 UAH2'000 UAH
Average annual costs5'000 UAH0 UAH
Project duration, incl.6 months4 months
Deadline for developing a FFS1 month1 month
Implementation period5 months3 months
Service life360 months120 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget7'500'000 UAH3'002'000 UAH
Project cost (preparation and implementation)7'500'000 UAH3'000'000 UAH
For preparation1'500'000 UAH0 UAH
For implementation6'000'000 UAH3'000'000 UAH
Project operation and closure cost0 UAH2'000 UAH
For operation0 UAH2'000 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitосвітні послуги
Service Unit Cost14'423 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
21/04/2026SP-L-210426-CB364D1ACommunity SPInvestment Feasibility StudyIncludeIn modern conditions, the implementation of the project will have a significant positive impact on the quality of education.-