The purpose of the project:
Capacity building
Key spending unit
Ministry of Energy of Ukraine
Functional classification of expenditures and budget crediting
0433 - Електроенергетична галузь
Target priority of the government
010300 - Інтеграція енергостстем України та Європи (зокрема на збільшення фізичних можливостей з експорту/імпорту електроенергії з країн ЄС)
Score
5.313
Basic data
Problems
Current status, description of problems and needs for their solution
Ensuring the balance reliability of the UES of Ukraine, taking into account the acute shortage of maneuvering capacities and the lack of quick-acting reserves (according to the analysis and conclusions of the system operator). The solution to this problem is solved by the construction and commissioning of 1000 MW of shunting storage capacities.
A detailed description of the project goal and the way to achieve it
The goal of the project is the construction and commissioning of new highly maneuverable generating capacities of the GANP, which, in turn, will contribute to solving the problem of the shortage of maneuverable capacities in the UES of Ukraine, including in view of the prospective growth in demand for electric energy, a sharp increase in the capacity of facilities that use renewable energy sources, in particular, solar and wind power plants, and ambitious plans for their further development, determined by government decisions.
Coordination of the project with strategic documents
Sphere development strategies
1. Decree of the Cabinet of Ministers of Ukraine dated April 21, 2023 No. 373-r; "On the approval of the Energy Strategy of Ukraine for the period up to 2050"; Decree of the CMU of July 13, 2016 No. 552-r "Hydropower Development Program for the Period Until 2026."
Demand for the service and its dynamics
Category
Year
Rating
Measure
Project indicators
Indicator
Base value
Target value
Number of employees of the institution/organization
236
236
Other
2000
2000
Other
4
4
Risk assessment
Risk
Category
Degree
Probability
Strategy
Risks of failure to ensure the efficient operation of the gas station in the electricity market
Market risk
Minor
Low
Avoidance
Risks of financing the Project and return on investment
Financial risk
Minor
Low
Reduction
The risk associated with changes in the exchange rate of the national currency and the currency of the loan
Economical risk
Considerable
Medium
Avoidance
Risks related to the technical and technological aspects of the Project implementation
Technical risk
Minor
Low
Reduction
The risk associated with the recognition of the results of the assessment of the Project's impact on the environment
Ecological risk
Minor
Low
Avoidance
Project plan
Feasibility study
Technical design
514 days
337 days