The purpose of the project:
Capacity building
Key spending unit
Ministry of Energy of Ukraine
Functional classification of expenditures and budget crediting
0432 - Нафтогазова галузь
Target priority of the government
990100 - Інші пріоритети Уряду
Score
3.56375
Basic data
Problems
Current status, description of problems and needs for their solution
The existing equipment is partially destroyed as a result of missile attacks on the infrastructure from the Russian side, is not efficient enough in terms of the depth of processing (currently, the depth of oil processing in the light of petroleum products is about 74%), emits significant volumes of greenhouse gases and limits the possibilities of increasing the volume of oil processing to cover most of the domestic Ukrainian market's demand for petroleum products.
A detailed description of the project goal and the way to achieve it
The goal of the project is the comprehensive modernization of the Kremenchug Refinery to increase the volume and depth of processing and, as a result, to overcome the critical dependence of the Ukrainian economy on the import of petroleum products.
Coordination of the project with strategic documents
Sphere development strategies
Energy strategy of Ukraine for the period until 2050 (approved by the Decree of the CMU of April 21, 2023 No. 373-r)
Demand for the service and its dynamics
Category
Year
Rating
Measure
Project indicators
Indicator
Base value
Target value
Bandwidth
11000000
11000000
Number of people to use the service
10
10
Number of jobs, including for IDPs
100
100
Project plan
Implementation
Feasibility study
Budgeting
Preparation
Technical design
Assessment
Appraisal
Financing
913 days
274 days
272 days
90 days
59 days
59 days
30 days
30 days