Construction of power units No. 5, 6 with the AR1000 reactor unit at the site of the Khmelnytsky NPP
The purpose of the project:
Other
Key spending unit
Ministry of Energy of Ukraine
Functional classification of expenditures and budget crediting
0433 - Електроенергетична галузь
Target priority of the government
010100 - Відновлення або ремонт пошкодженої ядерних реакторів/атомних електростанцій
Score
3.7995
Basic data
Problems
Current status, description of problems and needs for their solution
The need for the construction of new nuclear power units to replace the capacities of nuclear power plants that will be decommissioned after 2030 is determined by the "Energy Strategy for the period until 2050", which was approved by the decree of the CMU of April 21, 2023 No. 373-r.
A detailed description of the project goal and the way to achieve it
Ensuring Ukraine's energy independence and strengthening the country's role in the international electricity market. Increasing the electrical capacity of the Khmelnytskyi nuclear power plant.
The main purpose is the production of electricity at competitive prices. The commissioning of power units No. 5 and No. 6 of the Khmelnytskyi NPP will provide additional electricity supply to the energy system of Ukraine.
Coordination of the project with strategic documents
Sphere development strategies
Energy strategy of Ukraine for the period until 2050, approved by the order of the Cabinet of Ministers of Ukraine dated April 21, 2023 No. 373-r;
Demand for the service and its dynamics
Category
Year
Rating
Measure
Annual demand for services/infrastructure
2023
154826
GWh
Project indicators
Indicator
Base value
Target value
Number of jobs, including for IDPs
0
1156
Risk assessment
Risk
Category
Degree
Probability
Strategy
Implementation of the project on schedule
Other risk
Considerable
Medium
Avoidance
An increase in the cost of the project due to rising inflation and an increase in the exchange rate
Other risk
Considerable
High
Reduction
Funding deficit
Other risk
Considerable
Medium
Avoidance
Purchase of basic equipment
Other risk
Considerable
Low
Avoidance
Project plan
Information is absent