Project "Rehabilitation of Hydroelectric Power Stations" PJSC "Ukrhydroenergo"


The purpose of the project:

Capacity building

Key spending unit
Ministry of Energy of Ukraine
Functional classification of expenditures and budget crediting
0433 - Електроенергетична галузь
Target priority of the government
010300 - Інтеграція енергостстем України та Європи (зокрема на збільшення фізичних можливостей з експорту/імпорту електроенергії з країн ЄС)
Score
5.9075

Basic data

Detailed description of the project

The project involves reconstruction works at six hydroelectric power stations on the Dnipro River in Ukraine. These works include reconstruction of turbines, generators, replacement of electromechanical and hydromechanical equipment.

Problems

Current status, description of problems and needs for their solution
PrJSC "Ukrhydroenergo" is the main hydropower generating company of Ukraine, which provides coverage of peak loads in the daily schedule of the power system, frequency and power regulation, and is an emergency reserve in the combined power system. Taking into account the significant period of operation of equipment and hydraulic structures, further operation of hydroelectric units without continuing complex reconstruction would lead to a decrease in the capacity and electricity generation of hydroelectric power plants and hydroelectric power plants, an increase in operation and maintenance costs, a decrease in the reliability and safety of operation of equipment and structures, an increase in the emergency outputs of the equipment with an ever-increasing volume of repair and restoration works.
A detailed description of the project goal and the way to achieve it
Bringing the existing modes of operation of hydroelectric power plants, gas power plants PJSC "Ukrhydroenergo" to European standards, in particular, extending the operating life of hydroelectric units, improving the operational stability and reliability of power supply, increasing the regulatory capacity of UES, increasing the efficiency and level of safe operation of hydroelectric power plants and gas power plants, ensuring the safety of electricity supply to consumers .

Coordination of the project with strategic documents

Sphere development strategies
Decree of the CMU of April 21, 2023 No. 373 On the approval of the Energy Strategy of Ukraine for the period until 2050

Involved organizations

Organization
MINISTRY OF ENERGY OF UKRAINE
Roles
  • Project author
  • An initiator
  • Beneficiary
EDRPOU code
37552996
Organization
PRIVATE JOINT STOCK COMPANY "UKRHIDROENERGO"
Roles
  • A balance holder
  • An executor
  • An initiator
EDRPOU code
20588716

Demand for the service and its dynamics

Category
Year
Rating
Measure
Annual demand for services/infrastructure
2016
9.8
MW
Annual demand for services/infrastructure
2019
5.3
MW
Annual demand for services/infrastructure
2018
7
MW
Annual demand for services/infrastructure
2017
2.8
MW
Annual demand for services/infrastructure
2024
3.5
MW
Annual demand for services/infrastructure
2015
13.5
MW
Annual demand for services/infrastructure
2021
14
MW
Annual demand for services/infrastructure
2025
24.5
MW
Annual demand for services/infrastructure
2014
7
MW
Annual demand for services/infrastructure
2013
36.5
MW
Annual demand for services/infrastructure
2023
13
MW
Annual demand for services/infrastructure
2020
20.8
MW

Project indicators

Indicator
Base value
Target value
pip.indicators.other
843
921

Risk assessment

Risk
Category
Degree
Probability
Strategy
Technical risk (destruction of equipment, station building, engine room, dam, etc.)
Technical risk
Critical
High
Reduction
Impact on the environment due to the destruction of the dam
Ecological risk
Critical
High
Reduction
Loss of key specialists involved in the implementation of the Project
Operational risk
Minor
Low
Reduction
Oil spilled into the river due to equipment damage
Ecological risk
Minor
Medium
Avoidance
Termination of financing of the Project with MFI funds
Financial risk
Minor
Low
Avoidance

Project plan

Implementation
Budgeting
Technical design
Assessment
Feasibility study
Appraisal
Preparation
Financing
4687 days
449 days
212 days
182 days
153 days
151 days
63 days
7 days

Documents

Name
Date
About the ratification of the Credit Agreement (Project _Rehabilitation... _ dated 18.09.2012.pdf
Common document
20.08.2024
13:04:17 UTC
On the ratification of the Financial Agreement _Project _Rehabilitation of guides... - Law No. 685-VII dated November 19, 2013 - d413195-20131119.pdf
Common document
20.08.2024
13:09:17 UTC

Gallery

DREAM Code

DREAM-UA-200824-DCF62DFA

Status

Active

Create date

20.08.2024

Estimated budget

15'267'720'512,00

Project creator

MINISTRY OF ENERGY OF UKRAINE

Initiator

MINISTRY OF ENERGY OF UKRAINE. PRIVATE JOINT STOCK COMPANY "UKRHIDROENERGO"

Implementer

PRIVATE JOINT STOCK COMPANY "UKRHIDROENERGO"

Project implementation period

12.12 - 12.25

Geography

Kam’ianske. Zaporizhzhia. Vyshhorod. Svitlovodsk. Nova Kakhovka. Kaniv

Classification of sectors of economic activity according to the taxonomy of the World Bank

LH - Renewable Energy Hydro