Construction of protective structures against damage by unmanned aerial vehicles and missiles at energy infrastructure facilities
The purpose of the project:
Other
Key spending unit
State Agency for Reconstruction and Development of Infrastructure of Ukraine
Functional classification of expenditures and budget crediting
0260 - Інша діяльність у сфері оборони
Target priority of the government
010801 - Забезепчення захисту інфраструктури в підсекторі "Електроенергетика"
Score
5.2036
Basic data
Problems
Current status, description of problems and needs for their solution
The main problem is the increased vulnerability of electrical substations to damage by an aggressor, which can cause serious damage to the infrastructure. The lack of adequate protection threatens mass power outages and significant economic losses for its restoration. In case of damage, restoration of substations will require significant resources and time, which will worsen the situation in the energy system. This, in turn, will affect the livelihood of the population, the operation of critical facilities for the economy and the state's defense capability. The problem becomes especially relevant in the conditions of a long military conflict, when the risk of attacks remains high. Without proper resolution of these issues, the country risks losing the stability of its energy supply, which will have serious consequences for national security.
A detailed description of the project goal and the way to achieve it
The goal of the project is to ensure reliable protection of electrical substations from attacks by an aggressor, which will allow maintaining the stability of the energy supply.
To achieve this goal, protective structures will be built at 22 electrical substations in 14 regions of Ukraine. Currently, electrical substations do not have adequate protection, making them vulnerable to attack, and this poses significant risks to the power system of the entire country.
Implementation of the project will make it possible to eliminate this gap, ensuring the necessary level of security and stability of critical infrastructure. Thus, the project will make it possible to reach the target state in which the energy system will be able to function stably even in crisis conditions.
Coordination of the project with strategic documents
Activity program of the Cabinet of Ministers of Ukraine
The procedure for the implementation of the experimental project on the construction, repair and other engineering and technical measures for the protection of critical infrastructure objects of the fuel and energy sector of critical infrastructure
Priority action plan of the governmentClause 347 of the Plan of Priority Actions of the Government for 2024 approved by the Order of the Cabinet of Ministers of Ukraine of February 16, 2024 No. 137-r
Demand for the service and its dynamics
Category
Year
Rating
Measure
Project indicators
Indicator
Base value
Target value
Information is absent
Risk assessment
Risk
Category
Degree
Probability
Strategy
Lack of funding for project implementation
Financial risk
Critical
High
Acceptance
Project plan
Implementation
Budgeting
Financing
Appraisal
Assessment
Preparation
822 days
151 days
92 days
62 days
30 days
15 days